How do you account for a project under construction?

  Pub Date:2008-04-14 00:00:00 Author: Click:4 Category: amortize

I will assume that the project under construction is a major rebuilding of equipment or an addition to a building. The amounts spent on these projects would be debited to a long term asset account such as Construction Work in Progress. This account is often reported as the last line within the balance sheet classification Property, Plant and Equipment.

There will be no depreciation until the project is completed and the asset is placed into service. When the completed asset is placed into service, the project’s cost will be removed from the account Construction Work in Progress and will be debited to the appropriate plant asset account.

Relational Links
Category: amortize     Relational LinksOriginal Tex Move Links Del Edit
Tagamortize
KeyWords: calculators personal loans home equity lender personal finance jack guttentag money talks borrower defaults discharge of indebtedness amortization table tuition loans income
Hot Tag
Google
The articles on our site are all from Internet.To show the original,please click the "Original Text" at the end of the article.If the content of the article violated your copyright, please contact us.We will handle it immediately.The content on our site does not present our opinions, this site has nothing to do with the content.     PowerBy somefeel.org